Objective: Replacement of Floating Production Storage and Offloading (FPSO) Mooring lines Project.
Challenge: Client's Mooring Line Removal Method Statement is unable to effectively communicate procedures. A detailed Simulation/Animation was required, showing processes, equipment utilised, vessel and Diver position, at every stage.
Value added/Benefits
Animated videos served as a visual brief, clarifying every stage of the project.
Effectively identify potential hazards.
Assess risk to FPSO, installation vessels, dive vessels and Divers.